Projec.Net: Cambiar jornada laboral de un proyecto

Pregunta:

Hi,

I've created a task with the next properties:

* Fixed Units
* Effort Driven
* Start date: 5/20/10
* Finish date: 5/21/10
* Duration 5 hours


But automatically, the PNET chages the Start Date to 5/21/2010 and adds a constraint "Finish No Earlier Than" and Constraint Date "5/21/10" anf "17:00"

In my job, I finish at 15:00, how can I change? Thanks

Respuesta 1:

For the project: Workplan >> Properties >> Change Working Times

Conclusión: Buena solución y sencilla para la versión 9.1 de este software.